From the City of Aliso Viejo:
Construction on Aliso Creek Road between Enterprise and Pacific Park continues on schedule, with pavement milling beginning on Monday, September 9 and ending Wednesday, September 11.
The street's first layer of asphalt is scheduled to follow September 12-13, with the final asphalt layer scheduled for Saturday, September 14 and Monday, September 16. Two travel lanes in each direction of Aliso Creek Road and Pacific Park Drive are expected to be closed from 9 a.m. to 6 p.m. Motorists can expect traffic delays and are encouraged to take alternate routes.
All construction is dependent on the weather. Stay tuned for additional updates. The City appreciates the public's cooperation and patience during this road rehabilitation project.  Â