This post was contributed by a community member. The views expressed here are the author's own.

Neighbor News

Crosskey Architect's Find 1913 Library "Worth Preserving"

New Canaan P&Z in Deliberation Now

Crosskey Architects LLC

750 Main St Hartford, CT 06103

860 724 3000

Find out what's happening in New Canaanfor free with the latest updates from Patch.

May 19, 2021

Lynn Brooks Avni, AICP

Find out what's happening in New Canaanfor free with the latest updates from Patch.

TO: Town Planner/Sr. Enforcement Officer, Town of New Canaan 77 Main St.

New Canaan, CT 06840

RE: Consultant Analysis – Preservation/Demolition of 1913/1930s New Canaan Library Building

Dear Ms. Avni:

Attached please find my report which addresses the questions and issues put forth in the document I received from you entitled ‘Consultant Analysis’. As discussed, my task was to review the New Canaan Library’s (NCL) P & Z application and the New Canaan Preservation Alliance’s (NCPA) materials, and to act as a neutral unbiased resource for the P&Z Commission to help them understand the ‘Pros & Cons’ of saving/demolishing the old 1913 Library and 1930s addition.

Site Visit & Building Review

On Friday May 14,2021, David Goslin, architect, and principal of Crosskey Architects, toured the site and 1913/1930s portions of the building to review existing conditions. He found the building to be in very good condition and well maintained with few areas of concern. A brief outline of conditions is as follows:

Exterior

Roof Shingles and EPDM – good condition

Masonry – very good condition, minor areas need spot repointing of mortar Windows & Doors – very good condition

Wood trim, portico, roof overhang and eaves ‐ very good condition Rain Leaders – very good condition

Paint – good condition, spot areas need touch‐up, repainting needed within 3‐5 years

Interior

Good condition but depending future user needs, may need reconfiguration or replacement

Structural Condition

Very good condition, foundations are in excellent condition and no problems were observed

Mechanical, Electrical & Plumbing

Utility services & equipment – replace once additions are removed

System distribution & fixtures ‐ Good condition but depending future needs, may need reconfiguration or replacement

Page | 1

RE: Consultant Analysis

Preservation/Demolition of 1913/1930s New Canaan Library Building

5/19/21

Response to Consultant Analysis Task Letter Questions

  • Review of NCL & NCPA Cost Estimates
    • Review the materials (including plans and narrative) submitted by the Library and determine whether the costs provided are an accurate reflection of the proposed cost to rehabilitate the 1913 and/or to demolish the structure. – NCL’s estimate makes some good points about planning a budget and cushioning it for unknowns that can arise during the development of the project. When planning a project, scope expansion can occur as a normal process as more information becomes known and problems/approaches to construction are thought out. Also, discoveries of unforeseen conditions can occur during project planning. It is good practice to develop early project estimates with adequate budgetary safety factors to prevent financial shortfall later in the project. However, NCL’s estimate is too high, has too much cushion to be realistic and lacks enough detail to support it. Refer to my estimate, Attachment A.
    • Review the materials submitted by the New Canaan Preservation Alliance and determine whether the costs provided are an accurate reflection of the proposed work to bring the 1913 building up to current code and make it habitable space for rent. – NCPA’s estimate is a more accurate estimate of the cost for renovating the 1913/1930s building. It lacks detail and specificity on the actual costs and amount of budgetary cushion included. Refer to my estimate, Attachment A.
    • Determine if the cost of abatement provided by the Library is the same whether they preserve or demolish the 1913 building. – Generally, costs of abatement of most common types of hazardous materials are approximately the same for total building demolition or building preservation. A general overview is as follows:
      • Cultural Benefits
        • provides a sense of place, community pride and identity distinct from other places
        • maintains stylistic diversity to New Canaan’s Architecture
        • maps or references the Town’s history of land development over time
        • part of the Town’s local heritage connecting us to the past creating a sense of community
        • association with significant events, activities and people
        • exemplifies period building techniques and materials that were used.
        • Meets/satisfies most of the POCD goals
        • provides an opportunity for study & learning through tangible embodiment of past design, construction materials and techniques
        • provides a reference for study on influences on present day
        • Improves property values
        • Provides stabilization and growth
        • Enhances cultural tourism to town center
        • Creates construction jobs
        • Adds rentable sf to town center
        • Potential to secure investment from outside of town
        • Potential for positive income stream
        • Potential to add to the Town’s the tax base
        • Reduces cost of the new library – demolition and dumping savings
        • Produces income for NCL if the building were sold to a private entity
        • furthers environmental sustainability – preserves resources, reduces waste generation/landfill
        • furthers smart growth ‐ buildings on the street, reinforcing a more urban ‘pedestrian friendly’ streetscape
    • Outline the costs (a range is helpful) to retrofit the 1913 building – See Attachment A for my scope and cost estimate. It is possible to preserve the building for less than the total estimate by just addressing the exterior shell scope of work, structural improvements and basic HVAC needs. Also, my estimate envisions a simple basic interior fit‐out, which could change depending on a specific tenant’s or user’s needs. Often, the tenant fit‐out of a building’s interior is financed by the tenant, so it should not impact the costs of my estimate.

Determine if the costs would be different if the 1913 building were to remain and only used for back of house facilities storage and maintenance. – The costs for the building exterior would be the same regardless of the interior use of the building. The cost of interior improvements is almost solely dependent on the reuse of the building. If it was used for storage, the only improvements necessary would be for modified MEP systems. Conversely, for an office, retail or restaurant use, significant interior changes and improvement would be required and desired by the new occupant. Often the cost of interior improvements to suit specific occupants are factored into the financial ‘deal’, the cost of which is born by the tenant/occupant through increased rent, mortgage, or cash contribution.

Asbestos Containing Materials (ACM) – For total building demolition, all ACM must be abated as hazardous materials prior to building demo. If the building is to be preserved and reused, all ACM should be abated and removed. There may be some instances where ACMs such as tile, mastics, plaster, etc. could remain if encapsulated. Although encapsulation saves money initially, it usually increases building maintenance and renovation costs for the future.

Lead Based Paint (LBP) – for most building occupancies the presence of LBP does not present a problem. LBP poses a particular hazard to children under age 6, so if a building will be used by that age group, minimally encapsulation is required but complete removal is strongly recommended. LBP is a problem for that age group if they ingest it and it gets into their

Page | 2

RE: Consultant Analysis

Preservation/Demolition of 1913/1930s New Canaan Library Building

5/19/21

bloodstream. This can happen by eating paint chips, chewing on LBP surfaces, or inhaling lead dust which could be present from wear surfaces such as operable wood window sashes, wood doors and frames, cabinet drawers, etc. If abated during demo or construction, there are 2 aspects to consider:

Worker protection – this is required for both building demo or preservation. The cost is generally the same for either project.

Material Disposal ‐ if the building is demolished, and general construction debris can be mixed appropriately in dumpsters so the TCLP (Toxicity Characteristics Leaching Procedure) tests do not have too high a concentration of LBP, disposal of LBP adds no cost to the project. If the building is preserved, LBP items can be encapsulated adding little or no cost to the project, or they can be fully abated. Removed LBP must be captured and disposed of as hazardous materials, adding cost to a project. LBP items may also be demoed and replaced in kind. Demoed material can be treated as general construction debris pending passing TCLP tests.

Polychlorinated Biphenyls (PCBs) – The cost of abating PCB’s is the same for building demo vs. preservation. If PCBs are found to be present in existing materials, they must be abated appropriately. When this testing occurs can have a significant impact on abatement costs.

Soil Contamination ‐ The cost of managing soil contamination is generally the same for building demo vs. preservation. Depending on the type of contamination it may be allowed to remain on site or may have to be removed. In rare instances contamination could occur under a building, which if removal of soil from site is required, could add cost and complexity to a preservation project.

B. Recommendation/Feasibility of Preservation

1. Review of material submitted by the Library

‐ it is feasible to preserve the 1913 building in situ? ‐ yes, it is possible to save the 1913 Library in its current location at reasonable cost and limited impact to the proposed new library.

‐ is the 1913 building considered intact? – It is not 100% of what it originally was when it was built in 1913 and 1930s, but most of the original building is present and many of its character defining features such as the building’s form and design, exterior envelope and materials (stone, brick, windows, trim), front portico, interior wall painting, wood flooring (under the carpet) still exist. Also, 50% of the south wall and most of the west wall appear to be present based on a comparison of the current and original floor plans. In my opinion the building has enough character defining features left to make it culturally, educationally, economically, and environmentally beneficial to the Town and is therefore ‘intact’.

‐have any parts have been removed and/or replaced with modern materials? – Yes, some of the original elements have been removed over the course of the building’s life.

Synthetic Roof slates have replaced what was probably original slate roofing. Front portico columns are reported to be fiberglass replicas of the original wood columns. Half of the South wall was removed when the 1979 addition was added. Many of the interior walls, doors and

Page | 3

RE: Consultant Analysis

Preservation/Demolition of 1913/1930s New Canaan Library Building

5/19/21

trim were removed. Some of the interior features, like the wood flooring, have been covered. A new steel and concrete stair leads to the basement in the approximate location of the original stair.

‐is the building worth preserving? –Yes. The building retains many of its character defining features, is in very good condition and provides many benefits listed below in item #2, ‘Pros’.

‐ If yes, clarify what would be required to preserve the building. – See Attachment A for my scope and cost estimate.

2. Provide pros and cons of preserving the 1913 library building in place:

Pros:

f) has unique characteristics that can be difficult to replicate in new buildings.

2) Educational Benefits

3) Economic Benefits

4) Environmental Benefits

Page | 4

RE: Consultant Analysis

Preservation/Demolition of 1913/1930s New Canaan Library Building

5/19/21

Cons:

  • Cultural

a. Reduces the new ‘Town Green’ size, reducing the size of seasonal outdoor events

2) Economic

3) Environmental –

C. Opinion of Scope of Work & Cost of preservation

Annual Maintenance & Operating Costs – Annual maintenance and operating costs vary and are dependent on the new use/occupancy of the building. For example, given the same building, a storage use costs less to maintain and operate than a restaurant use.

Maintenance and operating costs for the same use in a new building vs. a newly renovated building are approximately the same. One exception could be that the utility costs are higher in and older building. But if the building is newly renovated the building envelope can be thermally improved and new energy efficient equipment added minimizing or eliminating a difference in energy usage.

Maintenance and Operating expenses can be incorporated into the lease rate, recuperated, or paid directly by tenant/occupant and may include the following:

  • Utilities – gas, water, phone/internet and electricity.
  • Daily Maintenance ‐ costs to keep the building functioning, maintained & clean
  • Professional building management fees.
  • Property taxes
  • Costs of supplies, landscaping, cleaning, and janitorial services.
  • Insurance premiums and deductibles.
  • Labor costs, legal fees, and accountant fees.
    • If demolished, can the 1913/1930s Library be somehow memorialized? – If the old library is demolished, a memorial could be designed to recall the building’s location or some aspect(s) of the building, like its history, significance, materials, etc. The success, strength and meaning of a memorial will depend on the creativeness and quality of the design and its ability to keep remembrance of the old library alive. But in the end, it’s just a memorial and does not embody the meaning, cultural and educational value of the historic building.

Page | 5

RE: Consultant Analysis

Preservation/Demolition of 1913/1930s New Canaan Library Building

5/19/21

Long term maintenance costs for items such as exterior painting, reroofing, equipment replacement, etc. must be budgeted for annually based on the long‐term life cycle of the items and their eventual replacement costs. For the 1913/1930s Building, based on its very good condition and planned renovations per Attachment A, I estimate the following life:

EPDM Roofing – 20 years Synthetic Roof Shingles – 20 years Stone & Brick – 100 years

Wood Windows – 50 years Wood Trim & Cornices ‐ 50 years Exterior Paint – 8 years

Interior items – these will change with each building tenant/user MEP Systems – 20 years

2. Estimate the costs to move the building. Outline typical anticipated relocation scope of work.

– Moving the building to a new location greatly reduces the cultural value of the building. Its presence on its original site, in its original context has meaning as described above in ‘B.2 Pros’. By moving the building to a different site, the building loses some of its historical significance and cultural value. Estimated scope and cost for moving the building is included in Attachment B, which assumes moving to a nearby site. Costs can vary greatly depending on the new site’s location and number of obstacles along the travel path. The estimate does not include the cost of acquiring the new site.

Please feel free to contact me with any questions regarding the above or any further questions you may have on this matter. I hope I have been of some assistance in clarifying the issues. Thank you for this opportunity.

Sincerely,

William W. Crosskey II, AIA LEED AP Founder

Page | 6

PRELIMINARY PROJECT COST SUMMARY (Construction Schedule of Values) - Attachment A

Preservation of 1913/1930s New Canaan Library

PROJECT Number of Buildings Total Project Square Footage (GSF)

Date

New Canaan, CT

19-May-21

Location

LINE

DIV.

DIV./TRADE ITEM

ESTIMATED COST

REMARKS

1

2

Building Demolition

($112,000)

Credit for 100% building demolition (taken from Turner Construction Estimate)

2

2

Environmental

$0

Already part of NCL new construction scope

3

2

Grading & Excavation

$5,000

At new rear entry

4

2

Site Utilities

$12,000

New connections to existing onsite Utiliites

5

2

Paving, Walks & Signs

$85,000

Paving and walks per Simpson Plan. Credit from NCL?

6

2

Unusual Site Conditions

$0

7

2

Lawns & Plantings

$50,000

Plantings per Simpson Plan. Credit from NCL?

8

2

Temporary Shoring

$5,000

Allowance as needed

9

2

Selective Demolition

$14,400

At addition connections, interior demo

10

2

Allowance for Division 2

$0

11

3

Concrete

$5,000

For new rear entry

12

3

Allowance for Division 3

$0

13

4

Masonry

$175,000

Rebuild South Wall, reopen West wall openings, saffolding, misc repointing & repairs

14

4

Allowance for Division 4

$0

15

5

Metals

$11,000

Loose lintels for masonry openings, dunnage for RTU's

16

5

Allowance for Division 5

$0

17

6

Rough Carpentry

$39,500

rough framing for partitions, roof eave reconstruction, new rear entrance canopy

18

6

Finish Carpentry

$44,400

trim, roof eave reconstruction

19

6

Allowance for Division 6

$0

20

7

Moisture Protection

$1,000

21

7

Insulation

$0

22

7

Roofing

$44,000

new EPDM flat roof, new shingles at roof edge

23

7

Sheet Metal

$3,000

gutters & downspouts

24

7

Siding

$0

25

7

Allowance for Division 7

$0

26

8

Doors & Hardware

$11,000

New Exterior Rear Doors, Interior doors, hardware

27

8

Windows & Glazing

$40,000

New Windows at South & West Walls

28

8

Allowance for Division 8

$0

29

9

Acoustical Tile

$0

30

9

Drywall & Plaster

$26,000

New drywall ceilings & walls, plaster repairs

31

9

Ceramic Tile

$2,000

Bathroom floor

32

9

Wood Flooring

$27,500

New wood flooring & refinish exisitng flooring where salvageable

33

9

Resilent Flooring

$0

34

9

Painting

$40,000

Paint new roof eave, repaint existing trim and interior painting for tenant it-out

35

9

Carpet

$0

36

9

Allowance for Division 9

$0

37

10

Unit AC and/or Sleeves

$0

38

10

Specialties

$3,000

Bathroom Accessories

39

10

Allowance for Division 10

$0

40

11

Special Equipment (Specify)

$0

41

11

Cabinets & Vanities

$2,500

ADA vanity and countertop

42

11

Appliances

$0

43

11

Allowance for Division 11

$0

44

12

Blinds, Shades & Artwork

$0

45

12

Allowance for Division 12

$0

46

13

Fire Suppression

$37,340

Depending on occupany, this may not be needed

47

13

Allowance for Division 13

$0

48

14

Elevators

$0

49

14

Allowance for Division 14

$0

50

22

Plumbing

$12,500

New plumbing for Bathroom

51

23

Hydronic Heating

$0

52

23

HVAC

$40,000

New heating & cooling system

54

23

Allowance for Division 23

$0

55

26

Electrical

$80,000

New electrical service, panels, wiring and fixtures and new fire alarm system throughout

56

26

Allowance for Division 26

$0

57

TOTAL IMPROVEMENTS

$704,140

58

1

General Requirements

$41,750

59

SUBTOTAL (Lines 57 & 58)

$745,890

60

Builder's Overhead & Profit (10%)

$70,414

61

SUBTOTAL (Lines 59 & 60)

$816,304

62

Building Permit & Other Fees (Specify)

$38,579

63

Bond Premium

$8,979

64

SUBTOTAL (Lines 61, 62 & 63)

$863,862

65

Architecture & Engineering

$81,630

10% of line 64

66

Contingency (10%)

$86,386

For unforseen conditions & construction phase contingency

67

SUBTOTAL (Lines 64, 65 & 66)

$1,031,878

68

Planning Contingency (25%)

$215,965

For scope development and expansion during project planning

69

TOTAL

$1,247,844

Z:\Projects\2118 - New Canaan Library\Documents\Reports\5-19-21 Attachment A - Scope & Cost Estimate \ Project Cost Summary Linked 1 of 1

PRELIMINARY COST ESTIMATE - Attachment A

May 19, 2021

Preservation of 1913/1930s New Canaan Library

Project

DIVISION

TRADE ITEM

QUANTITY

COST

TOTAL

  • GENERAL REQUIREMENTS
  • SITE WORK
  • CONCRETE
  • MASONRY
  • METALS
  • CARPENTRY
  • THERMAL & MOISTURE PROTECTION

General Requirements

Project Manager

1

$10,000.00

$10,000.00

Superintendent

1

$10,000.00

$10,000.00

Secretary

0

$0.00

$0.00

Vehicle Expense

1

$3,000.00

$3,000.00

Travel Expense

0

$0.00

$0.00

Snow Removal

1

$1,500.00

$1,500.00

OSHA Protection

1

$500.00

$500.00

Survey & Layout ( Site & Bldg.)

0

$0.00

$0.00

Weather Protection

1

$2,500.00

$2,500.00

Project Photographs

0

$0.00

$0.00

Dumpster (40CY)

8

$1,000.00

$8,000.00

Record Drawings

0

$0.00

$0.00

Broken Glass Repair

0

$0.00

$0.00

Temporary Toilets - one for less than 10 occ.

10

$75.00

$750.00

Temporary Fencing

1

$500.00

$500.00

Temporary Heat (Winter Cond'n)

1

$1,000.00

$1,000.00

Temporary Power, 11.8 KWH /mo.

1

$1,000.00

$1,000.00

Temporary Light, lamps, wiring, outlets

1

$1,000.00

$1,000.00

Temporary Office

0

$0.00

$0.00

Temporary Telephone

0

$0.00

$0.00

Temporary Fire Protection

0

$0.00

$0.00

Concrete Testing

1

$500.00

$500.00

Masonry Mix Testing

1

$500.00

$500.00

Construction Sign

0

$0.00

$0.00

Materials Storage

1

$1,000.00

$1,000.00

SUBTOTAL:

$41,750.00

Building Demolition

Building Demolition

1

-$112,000.00

-$112,000.00

SUBTOTAL:

-$112,000.00

Environmental

Lead-Based Paint Removal

$0.00

Urban Fill Removal & Disposal

$0.00

Asbestos Removal

$0.00

SUBTOTAL:

$0.00

Grading & Excavation

Exterior Excavation

$0.00

Exterior Backfill

1

$5,000.00

$5,000.00

$0.00

SUBTOTAL:

$5,000.00

Site Utilities

Water Supply & Trenching

1

$4,000.00

$4,000.00

Electrical, Cable TV

1

$4,000.00

$4,000.00

Sanitary Pipe, Trenching & Structures

1

$4,000.00

$4,000.00

SUBTOTAL:

$12,000.00

Paving

Bituminous Paving & Curbing

5,000

$15.00

$75,000.00

Walks &

Walks

1,000

$10.00

$10,000.00

Signs

$0.00

SUBTOTAL:

$85,000.00

Unusual Site

Conditions

$0.00

$0.00

SUBTOTAL:

$0.00

Lawns & Planting

Topsoil

$0.00

Seeding & Sodding

$0.00

Plantings

1

$50,000.00

$50,000.00

SUBTOTAL:

$50,000.00

Dismantle/ Shore Building

Dismantle, number, store materials

$0.00

Lifts

$0.00

Temporary Supports

1

$5,000.00

$5,000.00

$0.00

SUBTOTAL:

$5,000.00

Selective Demolition

Addition Connections

128

$75.00

$9,600.00

Interior Finishes

64

$75.00

$4,800.00

$0.00

SUBTOTAL:

$14,400.00

Allowance for Division 2 Site Work

$0.00

Allowance Scope

Concrete

Pad & foundation - new rear entrance canopy

1

$5,000.00

$5,000.00

$0.00

SUBTOTAL:

$5,000.00

Allowance for Division 3 Concrete

0

$0.00

Allowance Scope

Masonry

Masonry Repairs/Repointing

3,000

$15.00

$45,000.00

Rebuild SW Wall & 2 Piers at South & West Walls

500

$200.00

$100,000.00

Scaffolding

1

$15,000.00

$15,000.00

Reopen original openings on South & West Walls

200

$75.00

$15,000.00

SUBTOTAL:

$175,000.00

Allowance for Division 4 Masonry

$0.00

Allowance Scope

Metals

Loose Lintels at openings

6

$1,000.00

$6,000.00

Dunnage & Beams for new RTUs

1

$5,000.00

$5,000.00

SUBTOTAL:

$11,000.00

Allowance for Division 5 Metals

$0.00

Allowance Scope

Rough

Interior Partitions

1

$5,000.00

$5,000.00

Roof eave framing repairs at former additions

150

$70.00

$10,500.00

Repairs to roof sheathing

1,500

$6.00

$9,000.00

New Rear Entrance Canopy

1

$15,000.00

$15,000.00

$0.00

$0.00

$0.00

SUBTOTAL:

$39,500.00

Finish Carpentry

Rebuild Roof Fascia & Soffit

1

$20,000.00

$20,000.00

New Rear Entrance Canopy

1

$10,000.00

$10,000.00

New Window & Door Trim - Exterior

18

$400.00

$7,200.00

New Window & Door Trim - Exterior

18

$400.00

$7,200.00

SUBTOTAL:

$44,400.00

Allowance for Division 6 Carpentry

$0.00

Allowance Scope

Moisture Protection

Misc.

1

$1,000.00

$1,000.00

0

$0.00

$0.00

$0.00

SUBTOTAL:

$1,000.00

Insulation

$0.00

$0.00

SUBTOTAL:

$0.00

Roofing

Replace roof edge with new shingles

1,500

$15.00

$22,500.00

Roof at new rear entry

150

$10.00

$1,500.00

New EPDM at Flat roof

800

$25.00

$20,000.00

SUBTOTAL:

$44,000.00

Sheet Metal

Gutters and Leaders

1

$2,500.00

$2,500.00

Misc. Flashing

1

$500.00

$500.00

SUBTOTAL:

$3,000.00

Siding

$0.00

$0.00

SUBTOTAL:

$0.00

Allowance for Division 7 Thermal & Moisture

$0.00

Allowance Scope

DOORS & WINDOWS

Doors & Hardware

Exterior Doors

2

$2,500.00

$5,000.00

Interior Doors

10

$500.00

$5,000.00

Hardware

10

$100.00

$1,000.00

SUBTOTAL:

$11,000.00

  • DOORS & WINDOWS Cont.
  • FINISHES

Windows

Windows for South & West Walls

16

$2,500.00

$40,000.00

$0.00

SUBTOTAL:

$40,000.00

Allowance for Division 8 Doors & Windows

$0.00

Allowance Scope

Acoustical Tile

0

$0.00

$0.00

SUBTOTAL:

$0.00

Drywall & Plaster

New Drywall at walls

1,500

$4.00

$6,000.00

New Drywal at ceilings

2,500

$4.00

$10,000.00

Plaster Repairs

1

$10,000.00

$10,000.00

$0.00

SUBTOTAL:

$26,000.00

Tile Flooring

Bathroom Tile

100

$20.00

$2,000.00

$0.00

SUBTOTAL:

$2,000.00

Wood Flooring

Repair & Refinish

1,500

$5.00

$7,500.00

New Wood Flooring

2,000

$10.00

$20,000.00

SUBTOTAL:

$27,500.00

Res. Flooring

0

$0.00

$0.00

SUBTOTAL:

$0.00

Painting

Interior painting and new roof overhang

1

$20,000.00

$20,000.00

Exterior Painting - new and existing trim & windows

1

$20,000.00

$20,000.00

SUBTOTAL:

$40,000.00

0

$0.00

$0.00

SUBTOTAL:

$0.00

Allowance for Division 9 Finishes

$0.00

Allowance Scope

  • SPECIALTIES
  • EQUIPMENT
  • FURNISHINGS
  • SPECIAL CONSTRUCTION
  • CONVEYING SYSTEM

Unit A/C

$0.00

SUBTOTAL:

$0.00

Specialties

Bath Accessories

1

$3,000.00

$3,000.00

$0.00

SUBTOTAL:

$3,000.00

Allowance for Division 10 Specialties

$0.00

Allowance Scope

(describe here)

Special Equip.

0

$0.00

$0.00

SUBTOTAL:

$0.00

Cabinets

& Vanities

Bath Vanity & Countertop

1

$2,500.00

$2,500.00

$0.00

SUBTOTAL:

$2,500.00

Kitchen

Appliances

$0.00

$0.00

SUBTOTAL:

$0.00

Allowance for Division 11 Equipment

$0.00

Allowance Scope

Furnishing

$0.00

SUBTOTAL:

$0.00

Allowance for Division 12 Furnishings

$0.00

Allowance Scope

(describe here)

Special Construction

Fire Suppression

3,734

$10.00

$37,340.00

0

$0.00

$0.00

$0.00

SUBTOTAL:

$37,340.00

Allowance for Division 13 Special Construction

$0.00

Allowance Scope

Conveying Sys

Elevator

0

$0.00

$0.00

SUBTOTAL:

$0.00

Allowance for Division 14 Conveying System

$0.00

Allowance Scope

(describe here)

  • Plumbing
  • HVAC

Rough Plumbing

New Rough-in

1

$7,500.00

$7,500.00

0

$0.00

$0.00

0

$0.00

$0.00

SUBTOTAL:

$7,500.00

Finish Plumbing

New bathroom fixtures

1

$5,000.00

$5,000.00

0

$0.00

$0.00

$0.00

SUBTOTAL:

$5,000.00

Allowance for Division 22 Plumbing

0

$0.00

Allowance Scope

Hydronic

Heating

$0.00

$0.00

SUBTOTAL:

$0.00

Heating Ventilation A/C

New HVAC System

1

$40,000.00

$40,000.00

0

$0.00

$0.00

0

$0.00

$0.00

$0.00

SUBTOTAL:

$40,000.00

Allowance for Division 23 HVAC

0

$0.00

Allowance Scope

26 Electrical

Rough Electrical

New Electrical service, panels & wiring

1

$35,000.00

$35,000.00

0

$0.00

$0.00

0

$0.00

$0.00

$0.00

SUBTOTAL:

$35,000.00

Finish Electrical

Fixtures & Finish

1

$30,000.00

$30,000.00

Alarm System

1

$15,000.00

$15,000.00

$0.00

SUBTOTAL:

$45,000.00

Allowance for Division 16 Electrical

0

$0.00

Allowance Scope

% of Total

GENERAL REQUIREMENTS (Div. 01 from above)

$41,750.00

$41,750.00

OVERHEAD & PROFIT

$70,414.00

SUBTOTAL:

$112,164.00

5.9% 10.0%

Misc. Items:

BUILDING PERMIT

$20,619.84

INSURANCE

$17,958.69

BOND PREMIUM

$8,979.34

SUBTOTAL:

$47,557.87

ATTACHMENT B

5/19/2021

Scope & Cost for Moving the 1913/1930s New Canaan Library to a New Site

ESTIMATE

NOTES

Building Move Costs

Exacavate around building

$25,000

Trench around building; excavate and create ramp,

processed stone; backfill

Disconnect Utilities

$2,500

Selective Demolition

$15,000

Remove front entry portico

Building Move

$250,000

includes shoring as needed

$292,500

Route Relocation Costs

Drop Overhead Utility Lines

$15,000

Electric, Cable, Phone

Street lights - Electric Co.

$18,000

allowance for 20 street lights along route by Electric Co

Traffic Signals - Public Works Dept

$10,000

3 signals assumed

Police for traffic control

$10,000

Steel plates on street

$2,500

Place steel plates at potential soft spots on street

Tree Trimming

$5,000

Trim trees along route

$60,500

Work at New Location

Excavation & Backfill

$40,000

New Underground Utilities

$25,000

New Concrete Foundation

$75,000

New Wood Floor structure

$15,000

Masonry Repairs

$10,000

Rebuild Front Portico

$25,000

$190,000

General Requirements

Permits

$2,500

Traffic,Oversized load,Moving,Obstruction Permits

Insurance

$0

Insured under liability policy of Building Mover

Architecture & Structural Engineering

$25,000

Design of new floor and foundation

$27,500

SUBTOTAL

$570,500

General Conditions (5%)

$28,525

OH & P (10%)

$57,050

TOTAL MOVE COSTS

$656,075

]

The views expressed in this post are the author's own. Want to post on Patch?

More from New Canaan