Wilton Road Paving Status - Week Of July 6, 2020

The following roads are part of the proposed Paving program.

Press release from the Town of Wilton:

July 7, 2020

The following roads are part of the proposed Paving program.

Find out what's happening in Wiltonfor free with the latest updates from Patch.

Roads under "Roads in Progress" column indicates that drainage improvements began, and milling/paving will follow. Town began performing drainage improvements during the week of March 1, 2020. Road surfaces on these prepped roads may have raised structures until it is paved. Please travel on these roads with caution.

Roads under "Roads to be Scheduled" column indicates that work has not started, but are proposed to be included in this year's paving program, weather permitting.

Find out what's happening in Wiltonfor free with the latest updates from Patch.

The Town of Wilton will provide updates. Please continue to monitor the updates through the Town's website. Please contact Department of Public Works at (203) 563-0152 for further information.

IMPORTANT: The paving schedule may vary due to inclement weather.

Roads to be Scheduled:

Nod Hill Rd (partial) (Ridgefield Town line to Whipstick)

Roads In Progress:

Bhasking Ridge Rd

Brandon Cr

Cannon Rd

Chipmunk Ln

Coley Road

English Drive

Freshwater Lane

Gaylord Drive (S)

Hemmelskamp Rd

Henry Austin Dr

Kristine Lilly Way (Parital)

Orchard Dr

Raymond Lane

Salem Rd

School Rd (Partial)

Springbrook Ln

Surrey Glen

Washington Post Dr S

Wren Thicket

Roads Paved:

Bayberry Lane

Belden Hill Lane

Beldon Hill Rd N (partial) (Ridgefield Rd to Belden Hill Lane)

Black Birch Dr

Cider Mill Place

Glen Hill Ln

Glen Hill Rd

Graenest Ridge Road

Granite Dr

Ground Pine Road

Hidden Lake Ridge

Highview Drive

Hollow Tree Pl

Juniper Place

Ledgewood Dr

Mather St

New St 1

New St 2

New St Terrace

Oak Ledge Lane

Pheasant Run Rd

Rockhouse Rd

Scribner Hill Rd

Stonecrop La

Sunset Hill Rd

Thunder Lake Rd (Partial)

Walnut Place

Wildwood Drive

Woodchuck Lane

Woodhill Rd

2 Week Look Ahead
Starting week of July 6th, 2020 - The Towns paving subcontractor will be primarily working on
School Road (Partial), Kristine Lily Way (Partial), English Drive, Hemmelskamp Rd, Surrey Glen and Wren Thicket

There may be incidental work occurring on various other roads.


This press release was produced by the Town of Wilton. The views expressed here are the author's own.