Carmel Road Work Update
Phase three of construction along 116th Street will begin on or after Monday, Sept. 21.
September 17, 2020
Construction on two intersections from traffic signals to roundabouts continues at 116th Street & College Avenue and 116th Street & Guilford Road. Phase three of construction along 116th Street will begin on or after Monday September 21.
Find out what's happening in Carmelfor free with the latest updates from Patch.
At this time, all traffic will be rerouted to the north half of the intersections at Guilford and College. This Phase is expected to last approximately 35 days. No left-hand turns will be possible during this phase of work.