Town Of Dedham: Construction Updates June 11 2021

Eversource Gas:

06/11/2021 4:00 PM

Eversource Gas:

Find out what's happening in Dedhamfor free with the latest updates from Patch.

  • Lincoln Street; continue to work on services and have about 1 week left 
  • Adams Street:  Continue installing gas services.   Prepare to install valve in East Street
  • Elmwood Ave:  No work at this time.  Permit being Reviewed.  Work will begin in late June
  • Court Street Washington ST Wilson Ave construction to begin this week.  Contractor will be doing test holes and mobilizing.

Sprague Street Sidewalk Construction: 

  • Limits of work are from Cedar St to Greenlodge St and Cedar St to Dresser Ave
  • We will be grading and finish installing concrete sidewalks Tuesday and Wednesday.
  • Resident flyers will be dropped off for your notifications of concrete pours

Upland Rd and Top Hill Ave

Find out what's happening in Dedhamfor free with the latest updates from Patch.

  • Speed Hump Installation will be completed this week

Preston St and Lamoine St

  • Rochester Bituminous will be milling the roadway on Monday June 14th.  They will then adjust all the utility boxes and structures during next week.  We will apply the top course the following week. 
  • If a resident would like a tree planted in their front yard then please contact Jflanagan@dedham-ma.gov and we will meet and discuss the proper species for the location

Rustcraft Rd

  • Eversource Electric has installed the majority of the conduit.  
  • They will be onsite working on installing manholes and handholes
  • Expect traffic delays

Bridge and Ames Street Reconstruction

  • Paving will continue on Monday June 14th.
  • Tuesday the sidewalk work will begin on Bridge Street.
  • Utility Companies will continue to transfer their wires
  • If you have any issues with the construction on Bridge Street please contact Northern Construction   The Contact is Graham Johnson:
  • Office: (413) 289-1230 x209
  • gjohnson@northernconstruction.com

 Eastern Ave

  • The complete Streets project will begin on Monday June 14th.  We are beginning work on the East street side of Eastern Ave and will not interfere with the continued water service installation.
  • The first section of work will be the drainage installation of new manholes and catch basins.  
  •  If possible the Dedham Police will try to maintain two way traffic thru one lane.  
  • Expect Delays 

Pine Street

  • Work is continuing on the water main installation
  • Traffic will be allowed traveling from Needham towards Bridge Street as long as traffic can pass safely.
  • Expect Delays

Schiller Rd and Ridge Ave

  • Revoli Construction will be installing services on both streets.  They have about 4-6 weeks of work until the job is completed.  

If anyone has any questions on these projects please contact the DPW at 781-751-9350 or Jflanagan@dedham-ma.gov