Politics & Government

Town Of Dedham: Construction Updates June 17 2021

Eversource Gas:

06/17/2021 4:00 PM

Eversource Gas:

Find out what's happening in Dedhamfor free with the latest updates from Patch.

  • Lincoln Street; This work should be finished the week of June 21 
  • Adams Street:  No work at this time.  The remaining work will be after Elmwood Ave is complete.  
  • Elmwood Ave:  Work has started and will continue for the next 3 weeks.
  • Court Street Washington ST Wilson Ave construction.  This work will begin on Court Street at Richards Street and will continue towards Wilson Ave.

Sprague Street Sidewalk Construction: 

  • Limits of work are from Cedar St to Greenlodge St and Cedar St to Dresser Ave
  • Resident flyers will be dropped off for your notifications of concrete pours.  
  • The schedule has us finishing this section by June 30th.

Upland Rd and Top Hill Ave

Find out what's happening in Dedhamfor free with the latest updates from Patch.

  • Speed Hump Installation will be completed by June 25th

Preston St and Lamoine St

  • Rochester Bituminous will be adjusting structures on Monday and Tuesday. 
  • Rochester Bituminous will be paving the roads on Thursday or Friday Weather permitting. 
  • If a resident would like a tree planted in their front yard then please contact Jflanagan@dedham-ma.gov and we will meet and discuss the proper species for the location

Rustcraft Rd

  • Eversource Electric has installed the majority of the conduit.  
  • They will be onsite working on installing manholes and handholes
  • Expect traffic delays

Bridge and Ames Street Reconstruction

  • Sidewalk work will begin.  
  • Utility Companies will continue to transfer their wires
  • If you have any issues with the construction on Bridge Street please contact Northern Construction   The Contact is Graham Johnson:
  • Office: (413) 289-1230 x209
  • gjohnson@northernconstruction.com

 Eastern Ave - Complete Streets

  • The Drainage work will continue at various locations.
  •  Layout for and saw cutting for the granite curb will continue.
  •  If possible the Dedham Police will try to maintain two way traffic thru one lane.  
  • Expect Delays 

Eastern Ave - Water Project

  • The water main is complete.  
  • The contractor will be working on service connections the week of June 21.

Pine Street

  • Work is continuing on the water main installation and we are scheduled to be complete with the main installation the week of June 21.
  • Water Service connections will begin after the main is installed.
  • Traffic will be allowed traveling from Needham towards Bridge Street as long as traffic can pass safely.
  • Expect Delays

Schiller Rd and Ridge Ave

  • Revoli Construction will be installing services on both streets.  They have about 2weeks of work until the job is completed.  

If anyone has any questions on these projects please contact the DPW at 781-751-9350 or Jflanagan@dedham-ma.gov


This press release was produced by the Town of Dedham. The views expressed here are the author’s own.

More from Dedham