06/17/2021 4:00 PM
Eversource Gas:
Find out what's happening in Dedhamfor free with the latest updates from Patch.
- Lincoln Street; This work should be finished the week of June 21Â
- Adams Street: No work at this time. The remaining work will be after Elmwood Ave is complete. Â
- Elmwood Ave:Â Work has started and will continue for the next 3 weeks.
- Court Street Washington ST Wilson Ave construction. This work will begin on Court Street at Richards Street and will continue towards Wilson Ave.
Sprague Street Sidewalk Construction:Â
- Limits of work are from Cedar St to Greenlodge St and Cedar St to Dresser Ave
- Resident flyers will be dropped off for your notifications of concrete pours. Â
- The schedule has us finishing this section by June 30th.
Upland Rd and Top Hill Ave
Find out what's happening in Dedhamfor free with the latest updates from Patch.
- Speed Hump Installation will be completed by June 25th
Preston St and Lamoine St
- Rochester Bituminous will be adjusting structures on Monday and Tuesday.Â
- Rochester Bituminous will be paving the roads on Thursday or Friday Weather permitting.Â
- If a resident would like a tree planted in their front yard then please contact Jflanagan@dedham-ma.gov and we will meet and discuss the proper species for the location
Rustcraft Rd
- Eversource Electric has installed the majority of the conduit. Â
- They will be onsite working on installing manholes and handholes
- Expect traffic delays
Bridge and Ames Street Reconstruction
- Sidewalk work will begin. Â
- Utility Companies will continue to transfer their wires
- If you have any issues with the construction on Bridge Street please contact Northern Construction  The Contact is Graham Johnson:
- Office: (413) 289-1230 x209
 Eastern Ave - Complete Streets
- The Drainage work will continue at various locations.
- Â Layout for and saw cutting for the granite curb will continue.
-  If possible the Dedham Police will try to maintain two way traffic thru one lane. Â
- Expect DelaysÂ
Eastern Ave - Water Project
- The water main is complete. Â
- The contractor will be working on service connections the week of June 21.
Pine Street
- Work is continuing on the water main installation and we are scheduled to be complete with the main installation the week of June 21.
- Water Service connections will begin after the main is installed.
- Traffic will be allowed traveling from Needham towards Bridge Street as long as traffic can pass safely.
- Expect Delays
Schiller Rd and Ridge Ave
- Revoli Construction will be installing services on both streets. They have about 2weeks of work until the job is completed. Â
If anyone has any questions on these projects please contact the DPW at 781-751-9350 or Jflanagan@dedham-ma.gov