Eversource Gas:

06/25/2021 4:54 PM

Eversource Gas:

Find out what's happening in Dedhamfor free with the latest updates from Patch.

  • Lincoln Street; The gas main is installed.  Eversource will be removing old valve boxes.  
  • Adams Street:  No work at this time.  The remaining work will be after Elmwood Ave is complete.  
  • Elmwood Ave:  Work continues from Adams to Jefferson.  This work will continue thru July.
  • Court Street Washington ST Wilson Ave construction.  This wok is continuing on Washington St and continuing towards Richards Street.  

Sprague Street Sidewalk Construction: 

  • Limits of work are from Cedar St to Greenlodge St and Cedar St to Dresser Ave
  • The sidewalk work will be completed the week of July 25th

Rustcraft Rd Project

Find out what's happening in Dedhamfor free with the latest updates from Patch.

  • Eversource Electric has installed the majority of the conduit.  
  • They will be onsite working on installing manholes and handholes
  • RM Pacella will be doing tree work including trimming and clearing.  
  • Expect traffic delays

Bridge and Ames Street Reconstruction

  • Curbing and Sidewalk work will begin.  
  • The contractor will begin near Bingham Ave and will work towards Moseley's
  • Utility Companies will continue to transfer their wires
  • If you have any issues with the construction on Bridge Street please contact Northern Construction   The Contact is Graham Johnson:
  • Office: (413) 289-1230 x209
  • gjohnson@northernconstruction.com

 Eastern Ave - Complete Streets

  • The Drainage work will continue at various locations.
  •  If possible the Dedham Police will try to maintain two way traffic thru one lane.  
  • Expect Delays 

Eastern Ave - Water Project

  • The water main is complete.  
  • The contractor will be working on service connections.

Pine Street

  • The water main has been installed.  
  • Water Services will be installed in mid July.

Schiller Rd and Ridge Ave

  • Revoli Construction will be installing services on both streets. 
  • Water Services will be installed thru July 12