05/28/2021 2:30 PM
Eversource Gas:
Find out what's happening in Dedhamfor free with the latest updates from Patch.
- Lincoln Street; continue to work on services and will be another 2.5 - 3 weeks.
- Adams Street:Â Continue installing gas services.Â
- Elmwood Ave: No work at this time. Permit being Reviewed. Work will begin in June
- Court Street:Â construction to begin the end of June.
- Eastern Ave: Construction to begin end of June of July. This work will be coordinated with our Complete Streets Project.
Sprague Street Sidewalk Construction:Â
- Limits of work are from Cedar St to Greenlodge St and Cedar St to Dresser Ave
- We will be excavating and installing granite curb from Dresser Ave to Cedar St
- Resident flyers will be dropped off for your notifications of concrete pours
Annual Roads Program
Find out what's happening in Dedhamfor free with the latest updates from Patch.
- We are working with the contractor for a schedule for Fresno, Greensboro, Preston, Lamoine, Lower East Street, River Street, and Stoughton Rd.Â
- If a resident would like a tree planted in their front yard then please contact Jflanagan@dedham-ma.gov and we will meet and discuss the proper species for the location
Rustcraft Rd
- Eversource Electric is installing new conduit and they will be continuing for the next 4-5 weeks.
- They are beginning by the MBTA train station and will be installing new conduit connecting into existing conduit by the batting cages.
- They are continuing on this job. Â
- Expect traffic delays
Bridge and Ames Street Reconstruction
- Utility Companies will continue to transfer their wires
- Continue full depth construction on Bridge Street from McGolf towards the intersection of Pine St Ames St and Bridge Street
- Expect Traffic Delays
- Paving is scheduled for the first week of June. Â
- If you have any issues with the construction on Bridge Street please contact Northern Construction  The Contact is Graham Johnson:
- Office: (413) 289-1230 x209
 Eastern Ave from Whiting Ave to Rte 1
- The installation of the water main continues and the contractor is continuing towards Rte 1.
- The Rte 1 crossing will be at night the week of Sunday Night June 6th.
- There will be a crew installing services, hydrants and gate valves beginning this week
- If possible the Dedham Police will try to maintain two way traffic thru one lane. Â
- Expect DelaysÂ
Pine Street
- Work is continuing on the water main installation
- Pine Street will be closed to thru traffic from Bridge to Kiley. Traffic will be allowed traveling from Needham towards Bridge Street as long as traffic can pass safely.
- Expect Delays
Schiller Rd
- The Dedham Westwood Water District has one - two weeks left on Schiller Rd and then will move to Ridge Ave. Â
Â
If anyone has any questions on these projects please contact the DPW at 781-751-9350 or Jflanagan@dedham-ma.gov
This press release was produced by the Town of Dedham. The views expressed here are the author’s own.