GRAFTON, MA—Drivers in Grafton, take note.

Construction on the above roads will begin at 7 a.m. on Monday, July 16, instead of Tuesday, July 17. Work is scheduled to be completed by the end of the day on Thursday, July 19.

The schedule is as follows:

Find out what's happening in Graftonfor free with the latest updates from Patch.

  • Monday, July 16: Begin milling of Elliot Trail area (including Greta Lane, Heidi Lane and Jodi Lane).
  • Tuesday, July 17: Finish milling of Elliot Trail area. Begin paving of Stowe Road.
  • Wednesday, July 18: Begin Paving of Elliot Trail & area.
  • Thursday, July 19: Finish paving of Elliot Trail, Bruce Street and Pullard Road.

Police details will be on site; however, delays are expected.

Photo via Shutterstock

Find out what's happening in Graftonfor free with the latest updates from Patch.

Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

More from Grafton