Overnight Sewer Work In Easton Begins Next Week
Easton town officials said access to business will remain open throughout construction.

MANSFIELD, MA — Overnight work on gravity sewer main installation in connection with the Five Corners intersection will begin on Monday. The work is scheduled to take place between 8 p.m. and 6 a.m.
Work within the intersection will proceed north on Depot Street, progressing toward the intersection with Bay Road. The town said traffic will flow on directions around the work zone and that access will be allowed to all business throughout construction.
Testing of manhole structures and previously installed mains will take place on Foundry Stre from 9 a.m. to 3 p.m. This work involves service trucks and small crews set up in isolated areas the eastbound lane on Foundry Street.
Find out what's happening in Mansfieldfor free with the latest updates from Patch.
Traffic in both directions will be maintained by an alternating pattern around work zones using the westbound lane on Foundry Street. Brief and intermittent delays should be expected in both directions on Foundry Street.
Work will also continue at the pump station site located at 564 Foundry Street throughout the week. For more information about this project go here.