The Wright County Highway Department has released a general timeline for the CSAH 39/Odean Avenue construction project in Otsego. Dates are subject to minor changes due to weather conditions.

Find out what's happening in St. Michaelfor free with the latest updates from Patch.

Remainder of this week – re-spreading of topsoil, preparing concrete media and for curbing on the north side of CSAH and Odean.

Week of June 21 – Pouring concrete media and north curb on Odean roundabout.

Find out what's happening in St. Michaelfor free with the latest updates from Patch.

Week of June 28 – Placement of ADA ramps, intersection work and completion of pedestrian ramps

Week of July 5 – Paving base and binder work

Week of July 12 – Pave wear course

Week of July 19 – Permanent striping and signage.

The project is expected to be completed by the end of July.