MAPLEWOOD, NJ - Some new sidewalk pavers along Maplewood Avenue will put some spring in the step of residents and visitors of Maplewood Village when the work is completed.
The project, being done in tandem with traffic-calming bump outs on Maplewood Avenue’s west side will begin Monday.
During the course of the project the Township will advise of any loss of parking spots, and temporary closures of sidewalks and/or vehicular detours. During the project, materials and equipment will be staged in the upper Burgdorff parking lot, resulting in the temporary loss of some parking spots. The Maplewood Police Department will secure the staging area, and assist in any vehicular detours as needed during the project.
Find out what's happening in Maplewoodfor free with the latest updates from Patch.
The project schedule (subject to change due to inclement weather):
Oct. 1 through Oct. 5: Contractor will install curb bump outs at three intersections of the west side of Maplewood Avenue: at Durand Road, Baker Street, and Lenox Place. The bump outs will increase the sidewalk area and slow vehicular traffic. Sidewalks in these areas will be intermittently partially closed.
Find out what's happening in Maplewoodfor free with the latest updates from Patch.
Oct. 8-12: Contractor will install drainage improvements at the edge of the existing curbing and in the area of the newly-installed bump outs.
Oct. 17-Nov. 16: Contractor will begin removing the existing pavers and installing new ones. New curbing will be installed as necessary, e.g., to edge the new bump outs. The work will begin on the north end of Maplewood Avenue, in discrete blocks, starting at Durand Road, east to Woodland Road, and continue in this order: on Maplewood Avenue, east on Inwood Place; on Maplewood Avenue east on Highland Avenue; on Maplewood Avenue, east on Baker; finally, Maplewood Avenue south to Lenox Place.
There will be no construction or sidewalk/street impediments on Halloween and from Nov. 16 through Jan. 15 work will be suspended for the observance of holiday season.
Those with questions or concerns about the project can contact the Maplewood Business Administrator, Sonia Alves-Viveiros, at (973) 762-8120, ext. 2000
(Photo courtesy of Shutterstock)