The following are some high points of North Nashville Bikeway Progress:
January 24 2020
Find out what's happening in Nashvillefor free with the latest updates from Patch.
The following are some high points of North Nashville Bikeway Progress as requested:
Summary of work for January 20 through 24, 2020:
Find out what's happening in Nashvillefor free with the latest updates from Patch.
- No striping installed this week due to temperatures below 50 and wet conditions.
- Delineators approximately 75% complete on Ed Temple between Jefferson St and Buchanan St.
- Corrective work on ramp on DB Todd at Wheless.
- Met with Google for fiber relocation at DB Todd and Underwood prior to ramp work.
Two-Week look ahead:
- Complete delineator installation on Ed Temple Blvd between Jefferson St and Buchanan St.
- Striping to continue on Buchanan St/Garfield St and on Ed Temple at Jefferson St as weather allows (minimum temperature of 50 degrees and dry conditions).
- Complete sign installation on Arthur Ave.
- Concrete ramps and islands on Buchanan St at 11th Ave N & 14th Ave N, Garfield St at Delta Ave.
- Google to start relocation of fiber at DB Todd and Underwood prior to ramp work.