North Nashville Bikeway Progress Update

The following are some high points of North Nashville Bikeway Progress from the Project Manager.

Posted 1/31/2020

Find out what's happening in Nashvillefor free with the latest updates from Patch.

The following are some high points of North Nashville Bikeway Progress from the Project Manager:

Updates for January 27 through 31, 2020:

Find out what's happening in Nashvillefor free with the latest updates from Patch.

  • No striping installed this week.
  • Delineator installation completed on Ed Temple between Jefferson St and Buchanan St.
  • Corrective work on curb ramp on DB Todd at Wheless completed.
  • Met with Stansell to look at intersection work on DB Todd at both Jo Johnston and Jefferson St.
  • Laid out the new pedestrial pole location and called in for TN ONE CALL and determined the limits of concrete work.
  • Communications ongoing with Google regarding concrete work at DB Todd & Underwood. They came back with a 90 day relocation schedule. We responded that it needs to be done sooner than that and they are working on expediting their schedule.

Two-Week look ahead:

  • Striping to continue on Buchanan St/Garfield St and on Ed Temple at Jefferson St as weather allows (minimum temperature of 50 degrees and dry conditions).
  • Complete sign installation on Arthur Ave.
  • Concrete ramps and islands on Buchanan St at 11th Ave N & 14th Ave N, Garfield St at Delta Ave.
  • Continue Google communications for relocation at DB Todd & Underwood.
  • Lay out excavations for islands and curb work on Monroe to see if there are any Google conflicts.