North Nashville Bikeway Progress Update
The following are some high points of North Nashville Bikeway Progress from the Project Manager.
Posted 1/31/2020
Find out what's happening in Nashvillefor free with the latest updates from Patch.
The following are some high points of North Nashville Bikeway Progress from the Project Manager:
Updates for January 27 through 31, 2020:
Find out what's happening in Nashvillefor free with the latest updates from Patch.
- No striping installed this week.
- Delineator installation completed on Ed Temple between Jefferson St and Buchanan St.
- Corrective work on curb ramp on DB Todd at Wheless completed.
- Met with Stansell to look at intersection work on DB Todd at both Jo Johnston and Jefferson St.
- Laid out the new pedestrial pole location and called in for TN ONE CALL and determined the limits of concrete work.
- Communications ongoing with Google regarding concrete work at DB Todd & Underwood. They came back with a 90 day relocation schedule. We responded that it needs to be done sooner than that and they are working on expediting their schedule.
Two-Week look ahead:
- Striping to continue on Buchanan St/Garfield St and on Ed Temple at Jefferson St as weather allows (minimum temperature of 50 degrees and dry conditions).
- Complete sign installation on Arthur Ave.
- Concrete ramps and islands on Buchanan St at 11th Ave N & 14th Ave N, Garfield St at Delta Ave.
- Continue Google communications for relocation at DB Todd & Underwood.
- Lay out excavations for islands and curb work on Monroe to see if there are any Google conflicts.
Contact: TransportationPlanner@nashville.gov