The following are some high points of North Nashville Bikeway Progress from the Project Manager:

Work accomplished January 10 – January 14, 2020

Find out what's happening in Nashvillefor free with the latest updates from Patch.

  • The weather did not cooperate this week at all, again, either rain, wet, or temperature.
  • Demolition began for the concrete work on Buchanan St at 14th Ave N, and Buchanan St at 11th Ave N/Arthur St.
  • Communications ongoing with Google regarding concrete work at DB Todd & Underwood.

Two-week look ahead:

  • Striping to continue on Buchanan St/Garfield St and on Ed Temple from Jefferson St to Buchanan as weather allows (minimum temperature of 50 degrees and dry conditions).
  • Complete sign installation on Arthur Ave. once equipment is repaired.
  • Concrete ramps and islands on Buchanan St at 11th Ave N & 14th Ave N, Garfield St at Delta Ave. to continue.
  • Continue Google communications for relocation at DB Todd & Underwood.