Community Corner
City Of Hudson: 2nd St/Hwy 35 Update
Here's the work that is expected to take place this week, next week and beyond.

June 7, 2021
This week:
Find out what's happening in Hudsonfor free with the latest updates from Patch.
- Front Street to Coulee Road:
- Grading for pavement replacement
- Pouring concrete signal pole bases at Coulee Road
- Coulee Road to Vine Street:
- Concrete sidewalk and pavement at southwest corner of Locust Street and 2nd Street (Dunn Brothers’ Coffee corner)
- Finish up any remaining restoration on west side of the street through downtown area
- Vine Street to Lake Mallalieu:
- Finish water and sanitary sewer service lines between Myrtle Street and St Croix Street
- Storm sewer between Myrtle Street and St Croix Street
- (Hopefully) begin water and sanitary sewer main work between St Croix Street and Division Street
- North Hudson:
- Water and sanitary sewer service lines between Monroe Street and Michaelson Street
Next week:
- Front Street to Coulee Road:
- Pour concrete pavement and/or curb in front of wastewater treatment plant
- Coulee Road to Vine Street:
- Begin lighting conduit work on east side of the street in the downtown area
- Vine Street to Lake Mallalieu:
- Water and/or sanitary sewer main replacement between St Croix Street and Division Street
- Grading, curb, and sidewalk work between Myrtle Street and St Croix Street
- North Hudson:
- Finish water and sanitary sewer service lines between Monroe Street and Michaelson Street
- Storm sewer between Monroe Street and Michaelson Street
Further out:
Find out what's happening in Hudsonfor free with the latest updates from Patch.
- Work between Division Street and Lake Mallalieu - and related closures of the bridge to North Hudson - is still likely a few months away.
- Work between Myrtle Street and Vine Street is likely at least 3 weeks away.
This press release was produced by the City of Hudson. The views expressed here are the author’s own.