City Of Hudson: Second Street/Hwy 35 Update

The project team is working on tweaking the traffic signal timing at the Coulee Road intersection traffic signal.

(City of Hudson)

June 2, 2021

The project team is working on tweaking the traffic signal timing at the Coulee Road intersection traffic signal to alleviate the long back-ups out to Interstate 94. While the project team works on this, the team also asks that (1) if you are driving to North Hudson in the afternoon, please use the detour route via Minnesota Highway 95 if possible and (2) if you are driving to somewhere in Hudson outside of the downtown area in the afternoon, please consider using Exit 2 to make your way to wherever you are going if possible.

Find out what's happening in Hudsonfor free with the latest updates from Patch.

This week (week of June 1st):

  • Front Street to Coulee Road:
    • Grading for roadway pavement construction and restoration of the parking lot at Leverty Financial building
    • Continue to work on concrete bases, wiring, pull boxes, etc. for a new signal at Coulee Road intersection
  • Coulee Road to Vine Street:
    • Complete concrete sidewalk work on the west side of the road with the exception of the southwest corner of the Locust Street intersection and the driveway to Riverfront Center
    • Excavate and grade southwest corner of Locust Street intersection for concrete sidewalk installation
  • Vine Street to Lake Mallalieu
    • Construct water and sanitary sewer services between Myrtle Street and St Croix Street
    • Construct storm sewer between Myrtle Street and St Croix Street, including at both intersections
    • Potentially begin water and/or sanitary sewer main work between St Croix Street and Division Street
  • North Hudson
    • Continue with water and sanitary sewer services and storm sewer construction between Monroe Street and Michaelson Street

Next week (week of June 7th):

  • Front Street to Coulee Road:
    • Finish grading work
    • Pour concrete curb and pavement near the wastewater treatment plant.
  • Coulee Road to Vine Street:
    • Finish southwest corner of Locust Street intersection
    • Begin lighting work on the east side of the street
  • Vine Street to Lake Mallalieu:
    • Water and/or sanitary sewer mains from St Croix Street to Division Street
    • Grading and potential curb and/or sidewalk work between Myrtle Street and Division Street
  • North Hudson:
    • Potentially begin water and/or sanitary sewer work between Michaelson Street and Sommers Street (to be determined based on conversations with the Village)
    • Grading and potentially curb work between Monroe Street and Michaelson Street

For more information, please see the document below.Update 06/02/21 (PDF)


This press release was produced by the City of Hudson. The views expressed here are the author’s own.