Mount Pleasant Water Main Project Update
This week the Village of Mount Pleasant released an update on the project at Perry Avenue.
MOUNT PLEASANT,WI— This week the Village of Mount Pleasant released an update on the project at Perry Avenue.
Almost all pipe work is complete on Perry Avenue south of Washington, with the exception of the intersection of Wright and Perry. Storm sewer replacements are being complete and concrete pavement replacement is anticipated to begin this week.
The area between Washington and Kinzie has some 12” water main replacement to be completed.
Find out what's happening in Mount Pleasant-Sturtevantfor free with the latest updates from Patch.
The water main then needs to be tested and water service replacements will begin.
Pavement repairs will follow.
Find out what's happening in Mount Pleasant-Sturtevantfor free with the latest updates from Patch.
For the area between Kinzie and Graceland, some final 12 inch water main replacement is being completed.
The 48” water main in the area of Perry and Graceland will be completed in approximately the next 7 days. At that point pavement replacements will begin.
As for other ongoing projects, some will wrap up soon.
Paving should begin on Newman Road north and south of Spring Street, on Cherry Hill Drive and Cortland Avenue on November 2 and 3. Due to rain last Thursday and Friday, contractors were unable to pave as they hoped.
As for Fancher Road & Renaissance Blvd, paving is set for Saturday October 31 and Monday November 2.
For the project at Perry Avenue between Graceland Blvd & Kinzie Avenue, the contractor is going to try to get the paving done yet this week. It's important to note, Graceland Blvd will be closed from Ohio Street to Hwy 31 during this time. Once paving is complete contractors need to do the pavement markings.
Should the weather cooperate these roads should be complete the week of November 9.
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.