Hardscrabble, Chaffin Intersection To Close For 2 Weeks
The closure, which will start July 9, will help shorten construction time of the Hardscrabble Green Loop project by four to five months.

ROSWELL, GA — Starting July 9, the city of Roswell will close the intersection of Hardscrabble and Chaffin roads for two weeks to help shorten construction time of the Hardscrabble Green Loop project by four to five months.
During the road closure, the contractor will construct the roundabout at Hardscrabble and Chaffin roads. Through traffic will be required to detour around the Hardscrabble-Chaffin Road intersection during the two-week closure.
Detour routes will include Etris Road, Crabapple Road, State Route 92/W. Crossville Road, and King Road. Local residents will still be allowed access. Drivers will start to see signage alerting them to the impending closure and detours approximately two weeks prior to July 9.
Find out what's happening in Roswellfor free with the latest updates from Patch.

The entire Hardscrabble Green Loop project is slated to be finished in the spring or summer of 2019. The Hardscrabble Green Loop is a “complete street,” featuring intersection improvements, sidewalks, bikes lanes, and a multi-use trail.
Once complete, it will allow bicyclists and pedestrians to use both sides of Hardscrabble Road corridor. This concept is part of a larger bicycle and pedestrian system called the Roswell Loop. The cost of the entire project is $5.8 million and is jointly funded by the city and the Georgia Department of Transportation.
Find out what's happening in Roswellfor free with the latest updates from Patch.
(For more news like this, find your local Patch here. If you have an iPhone, click here to get the free Patch iPhone app; download the free Patch Android app here)
Image via Shutterstock
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.