Politics & Government
Rotary Removal In Methuen To Continue In March
Drivers should brace for traffic delays on I-93 and routes 113 and 110 in Methuen.

METHUEN – Driving on Interstate 93 and Routes 110 and 113 in the Methuen area will be more of a challenge during March as the Massachusetts Department of Transportation announced roadwork will continue where MassDOT has removed the rotary.
MassDOT has announced it will do the following:
- Continue work on utilities on Routes 110 and 113 west of Route 93
- Work on drainage in center work zone on I-93
- Continue to work on lighting on Route 110/113
- Continue to excavate for permanent sedimentation and infiltration basins
- Form and place median concrete deck sections at I-93 Bridge over Riverside Drive
- Place fill where center sections of existing rotary bridges have been removed
- Place permanent precast median barrier at I-93
- Form and place concrete barrier below Forest Street Bridge
Work hours:
Find out what's happening in Andoverfor free with the latest updates from Patch.
- For daytime work on I-93 – 5:30 a.m. to 5:30 p.m.
- For nighttime work on I-93 – 8:00 p.m. to 5:00 a.m.
- For daytime work on local roads – 7:00 a.m. to 3:30 p.m.
Expected Lane Closures:
- Single lane closures can be expected on I-93 northbound from 5:30 a.m. to 2:00 p.m.
- Single lane closures can be expected on I-93 southbound from 10:00 a.m. to 2:00 p.m.
- Double lane closures can be expected on I-93 southbound from 10:00 p.m. to 5:00 a.m.
- Single lane closures can be expected on local roads from 9:00 a.m. to 3:00 p.m.
Find out what's happening in Andoverfor free with the latest updates from Patch.
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.