The work on Ewingville Road, between Route 31 and Federal City Road, in Ewing Township, is expected to being today, March 20, and take about 10 days to complete, weather permitting.

The Mercer County Department of Transportation and Infrastructure is scheduled today (March 20) to begin milling and resurfacing work on Ewingville Road, between Route 31 and Federal City Road, in Ewing Township.
The work is expected to take about 10 days to complete, weather permitting.
On week days during the work period, that stretch of Ewingville Road will be closed to “through traffic” from about 9 a.m. to 3:30 p.m. Access for businesses and residents will be allowed, however.
Find out what's happening in Lawrencevillefor free with the latest updates from Patch.
The following detours will be in place:
- West End of Project: From Upper Ferry Road, make right onto Route 31 South, left onto Green Lane, left onto Ewingville Road to end of detour. From Route 31 North approaching project location, stay on Route 31 North, right onto Bull Run Road, right onto Federal City Road to Ewingville Road to end of detour.
- East End of Project: From Ewingville Road, make right onto Federal City Road, left onto Bull Run Road, left onto Route 31 South to Ewingville Road to end of detour. From Federal City Road approaching project location, make left onto Ewingville Road, right onto Green Lane, right onto Route 31 North to Ewingville Road to end of detour.