Westfield Doubles Down On Road Paving Projects
More than 90 roads and 18 miles of paving planned for 2019.
WESTFIELD, NJ - Westfield is poised to make a record number of road improvements this year with Tuesday night's approval of the 2019 capital budget, which includes $3.7M for the work in 2019.
Over the last nine years, the Town has paved an average of approximately four miles of roadway each year. This year, that figure will rise to more than eight total miles, 31 roads, marking an unprecedented effort in this area.
“I am a firm believer in putting residents’ tax dollars to work for them, and road improvements continues to be a top request that the Council members and I hear on a regular basis,” said Mayor Shelley Brindle. “The approval of this capital budget is the first step in making these improvements a reality to improve quality of life within Westfield.”
Find out what's happening in Westfieldfor free with the latest updates from Patch.
In addition to the municipal paving efforts, the Town also announced an agreement
with Elizabethtown Gas in which the utility will pave 9.82 miles of roadway on 59 roads that it has disrupted as part of its ongoing maintenance and repair work in various parts of Town over the course of the past 18 months.
“We’re very grateful for our continued strong partnership with Elizabethtown Gas,” Brindle said. “The road work that they’ve agreed to undertake is substantial and, notably, will mostly include curb-to-curb, full-width paving – versus the patching and partial road paving they have done in the past following completion of their work.”
Find out what's happening in Westfieldfor free with the latest updates from Patch.
A summary of improvements by ward follows below:
Ward 1
- Town Paving = 1.99 miles (8 roads or sections of road)
- Elizabethtown Gas Paving = 4.26 miles (23 roads or sections of road)
Ward 2
- Town Paving = 1.85 miles (5 roads or sections of road)
- Elizabethtown Gas Paving = 1.69 miles (14 roads or sections of road)
Ward 3
- Town Paving = 2.41 miles (11 roads or sections of road)
- Elizabethtown Gas Paving = .04 miles (1 section of road, as Ward 3 was spared the Elizabethtown Gas work in the past 18 months)
Ward 4
- Town Paving = 2.54 miles (7 roads or sections of road)
- Elizabethtown Gas Paving = 3.83 miles (21 roads or sections of road)
A full list of roads included on the 2019 paving list can be found here.
Other highlights of the capital budget include the refurbishment of the south side train station coffee hut, as well as additional pedestrian safety measures such as more ADA compliant ramps and pedestrian flashing beacons.
The vote for the final adoption of the capital budget is scheduled for May 21.
Thanks for reading! Learn more about posting announcements or events to your
local Patch site here. Have a news tip you'd like to share? Or maybe you have a press release you would like to submit or a correction you'd like to request? Send an email to russ.crespolini@patch.com
Subscribe to your local Patch newsletter by clicking here. You can also have them delivered to your phone screen by downloading our Apple iOS app here, or by visiting the Google Play store for the Android app here.
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.