Radnor Township Department of Public Works For a copy of the Recreation Department Weekly E-Newsletter, please click here
June 6, 2021
Radnor Township Department of Public Works
Find out what's happening in Radnorfor free with the latest updates from Patch.
REFUSE/RECYCLE/YARD/ BULK/HOLIDAY SCHEDULE:
- Monday – District 1 Refuse
- Tuesday – District 2 RefuseÂ
- Wednesday – Yard Waste & Bulk Trash Collection
- Thursday – District 1 Recycling
- Friday –District 2 RecyclingÂ
UTILITIES:
Find out what's happening in Radnorfor free with the latest updates from Patch.
- Gas Main work on Boxwood Rd and Barclay Rd. will continue through Q2 2021.
- February 10, 20201: Gas main work on Lenoir Ave. and Bloomingdale Rd. will continue until June 2021.
- March 8, 2021: Aqua will begin a 3-month water main replacement project on Barclay Rd. (weather dependent). They will be replacing 3156 Feet of pipe.
- April 12, 2021: Aqua will begin a 2-month water main replacement project on Gallagher Rd (weather dependent). They will be replacing 1200 Ft. of pipe.
- March 23, 2021: Aqua will begin a 4-month water main replacement work on Wyldhaven Rd. from Yorkshire Rd. to Ithan Ave., Marlbridge Rd., Brandymede Rd., and Hollybush Rd.
Recreation & Community Programing DepartmentÂ
Â
For a copy of the Recreation Department Weekly E-Newsletter, please click here
Radnor Township Department of Engineering
- Radnor TAP Trail
- Twice daily site visits to continue
- Weekly status meeting attendance
- Daily phone contact with McMahon & Associates
- Review of quantities for payment, change orders
- Possible close out walk through
- North Wayne Avenue Sidewalk Project Scheduling pre-construction meeting, after receipt of bonds
- Review Land Development Plans
- Pre-application meeting with Developer(s)
- Review projects inspections with the Township’s contracted inspection firm, QCI
- Obtain Easements for Lancaster Avenue Sanitary sewer project, West Wayne Sidewalk Project, Wayne/West Avenue Pedestrian Project, Gulph Creek Retaining wall
- Process payments for all Capital Projects
- Harford Trail closeout
- Brookside Storm Sewer Project revise easement layout
- Respond to builders’ and developer’s inquiries
- Perform Site Inspections
- Review land development application plans
- Continuing weekly meetings with consultants (Carroll, Gilmore, Gannett Fleming) on all infrastructure projects
- Process grading permitsÂ
- Process clearing permitsÂ
- Process sidewalk, and U&O applications
- Address resident concerns.
- Meet with residents in lobby regarding questions for permits, U & O, grading permits
- Respond to and meet with residents on various concerns, in most cases stormwater runoff/flooding
- Process, review, and approve invoices for payment to Finance Department
ABOUT RADNOR TOWNSHIP The mission of the Radnor Township government is to serve the best interests of all our residents by providing and maintaining a secure environment that enhances the quality of life for the individual and the community. We recognize the dignity of public service and are dedicated to the highest standards of integrity. We pledge to be a dynamic, responsive organization that continually strives to provide the most efficient and effective level of service for Radnor Township. Visit Radnor Township at: http://www.radnor.com Like us on Facebook: http://Facebook.com/RadnorTownship/ Follow us on Twitter: http://twitter.com/radnortownship Follow us on Instagram: http://instagram.com/radnortownshipFor more information, Press Only:Molly GallagherPress Information Officer610.688.5600 x 197