Traffic & Transit

U.S. 422 Lanes Close Next Week For Construction

Closures are set in both directions in Limerick and Lower Pottsgrove Townships for pavement repair.

Press release from PennDOT:

Jan. 29, 2021

U.S. 422 motorists will encounter a lane closure in both directions next week for various construction activities under a project to rehabilitate pavement and repair seven structures along a five-mile section of U.S. 422 between the Royersford/Trappe and Sanatoga interchanges in Limerick and Lower Pottsgrove townships, Montgomery County, the Pennsylvania Department of Transportation (PennDOT) announced today.

Find out what's happening in Tredyffrin-Easttownfor free with the latest updates from Patch.

The work schedule and locations are:

  • Monday, February 1, through Friday, February 5, from 6:00 AM to 2:00 PM, a left or right lane closure is scheduled on westbound U.S. 422 between Country Club Road and Evergreen Road and at the Sanatoga Interchange; and
  • Monday, February 1, through Friday, February 5, from 10:00 AM to 6:00 PM, a left or right lane closure is scheduled on eastbound U.S. 422 between Park Road and Township Line Road and at the Limerick and Sanatoga interchanges.

Motorists are advised to allow extra time when traveling through the work areas because backups and delays will occur. All scheduled activities are weather dependent.

Find out what's happening in Tredyffrin-Easttownfor free with the latest updates from Patch.

Work on this project will be in accordance with Centers for Disease Control and state Department of Health guidance as well as a project-specific COVID-19 safety plan, which will include protocols for social distancing, use of face coverings, personal and job-site cleaning protocols, management of entries to the jobsite, special signage and relevant training.

Under this two-year improvement project, PennDOT’s contractor will mill, overlay and rehabilitate existing U.S. 422 pavement; perform bridge deck repairs, concrete and joint patching, sealing and drainage improvements; install new guide rail and rumble strips; and repair or replace damaged traffic signs along the corridor.

H & K Group Inc. of Skippack, Montgomery County is the general contractor on the $19.1 million project which is financed with 100 percent federal funds. The entire project is expected to be completed in late 2021. For information, visit www.422improvements.com.

For a complete list of construction projects impacting state-owned highways in Bucks, Chester, Delaware, Montgomery and Philadelphia counties, visit www.penndot.gov/District6TrafficBulletin.

To help make decisions regarding winter travel, motorists are encouraged to "Know Before You Go" by checking conditions on more than 40,000 roadway miles, including color-coded winter conditions on 2,900 miles, by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 1,000 traffic cameras. Users can also see plow truck statuses and travel alerts along a specific route using the "Check My Route" tool.