Aberdeen Undertakes Biggest Road Repair Project Since 1960s
A total of 22 road construction projects will take place in Aberdeen Twp. this year, from Cashel Drive to the Line Road border with Holmdel.
ABERDEEN, NJ — Aberdeen Township announced Wednesday that a total of 22 road construction projects will take place this year, calling it the most significant investment in Aberdeen's roads since the 1960s.
Full reconstruction projects on five roads — including new curbs, drainage and sewers — are already in progress on Wayside Drive, Cashel Drive, Carol Lane, Crystal Place and Claire Court, according to Deputy Mayor Robert Swindle.
The next undertaking will encompass nine mill-and-pave projects on Orchard Street, Alden Court, Blair Road, Hyer Court, Halleran Court, Heather Glen Drive, Mathiasen Avenue, Jeter Street and Church Street. Residents can expect that work to begin in August and be completed in October.
Find out what's happening in Matawan-Aberdeenfor free with the latest updates from Patch.
“After severe winters, these repairs are badly needed and this year the Township Council resolved to undertake the biggest road program in Aberdeen since 1967,” Swindle said. “The Council also revamped the program to focus more on mill-and-pave projects that cost less and preserve our roads longer.”
Reconstructions of six more roads will also begin in 2019. Projects on Sherwood Road, Ambler Lane, Dawn Way, and Ambler Court will cover their entire length of the streets. The other projects cover partial sections on Deerfield Lane, from Deborah Lane to Drexel Lane, and Cliffwood Avenue, from Sweetbriar Street to Lenox Road.
Find out what's happening in Matawan-Aberdeenfor free with the latest updates from Patch.
“Because more than half of Aberdeen’s roads were built between 1952 and 1967, the Township Council has been planning for years to utilize revenue from new redevelopments to re-invest in our aging infrastructure,” said Councilman Greg Cannon. “As a result, in 2019, the Council is greatly accelerating the Township’s road program without taking on any unplanned or emergency debt.”
Under a shared services agreement with Holmdel, Line Road will also be repaved along the Aberdeen-Holmdel border from Church Street to Van Brackle Road, with construction scheduled for October 2019.
Finally, the Township will complete the fourth of five phases to repave County Road, using grants obtained from the State Department of Transportation for the fourth straight year.
“To date, the Township has obtained $990,000 to repave County Road without using local tax dollars,” said Councilwoman Connie Kelley. “Now that grants have been exhausted, the Township will wrap up the repaving of all sections of County Road in 2020 during the fifth and final phase.”
Residents on the affected streets will receive hand-delivered notices from the Township Engineer, CME Associates, informing them of the scope of the work and approximate timetable.
“With our contractors working in tandem with our Police and Public Works Departments, all efforts are made to minimize the disruptions that such projects can create. But as our prior road projects have demonstrated, the temporary pain will pay dividends in terms of enhanced curb appeal for homeowners and a smoother ride for motorists and bicyclists,” said Councilman Artie Hirsch.