Town Of Los Gatos: PG&E Gas Line Replacement Work

Daleo Inc., a contractor working under the direction of PG&E, will be upgrading approximately 2,650 ft. of gas main along Main Street in ...

May 27, 2021

Daleo Inc., a contractor working under the direction of PG&E, will be upgrading approximately 2,650 ft. of gas main along Main Street in two simultaneous phases.

Find out what's happening in Los Gatosfor free with the latest updates from Patch.

Phase 1 work covers W. Main St. between University Ave. and the Highway 17 Overcrossing, including Park Ave. This phase begins June 7, 2021 with a projected completion date in early August.  

Phase 2 construction will begin in mid-June at the intersection of E. Main St. at Pleasant St. and Jackson St.  The work will proceed northeast up Los Gatos Blvd., then head west on Simons Way to Bella Vista Ave. The projected completion date for this phase is in September.  

Find out what's happening in Los Gatosfor free with the latest updates from Patch.

There will be partial lane closures with traffic control.  

This work allows PG&E to upgrade and strengthen the gas distribution infrastructure in Los Gatos and replace gas services in order to continue to provide safe and reliable natural gas to the community.  

PG&E will coordinate notifications to customers related to any gas service interruptions.  For questions, please email the PG&E project manager, Travis Muccigrosso-White, at tcmh@pge.com.